   Stop Notice #1 [ Back to Contract #04163734]     [ Top of Page ]  

  Claimant:
Universal Roll Forming, Inc.
PO Box 699
Pleasant Grove, UT  84062
                                                

    History:
Claim establisted for $22,053.63
on 12/27/2010 by s130442

Release Claim - Letter of Release
 on 01/04/2011, by s130442
$0.00 Paymt to contract payee
                                                
  ***  Claim Date: 12/17/10
 

  
   Stop Notice #2 [ Back to Contract #04163734]     [ Top of Page ]  

  Claimant:
RCJ & Associates, Inc.
PO Box 1896
Elk Grove, CA  95624
                                                

    History:
Claim establisted for $173,123.75
on 10/14/2011 by s130442

Release Claim - Letter of Release
 on 10/27/2011, by s130442
$0.00 Paymt to contract payee
Stop notice filed in error.
                                                
  ***  Claim Date: 10/13/11
 

  
   Stop Notice #3 [ Back to Contract #04163734]     [ Top of Page ]  

  Claimant:
Roadway Engineering Works, Inc
3442 6th St
Ceres, CA 95307
                                                

    History:
Claim establisted for $99,067.40
on 10/25/2011 by s130442

Release Claim - Letter of Release
 on 11/16/2011, by s130442
$123,834.25 Paymt to contract payee
Schedule: 2DXXX210
                                                
  ***  Claim Date: 10/24/11
 

  
   Stop Notice #4 [ Back to Contract #04163734]     [ Top of Page ]  

  Claimant:
RCJ & Associates, Inc.
PO Box 1896
Elk Grove, CA  95624
                                                

    History:
Claim establisted for $173,123.75
on 11/01/2011 by s130442

Release Claim - Court
 on 03/20/2012, by s130442
$109,680.26 Paymt to contract payee
Schedule: 2DXXX440
Per court order, release funds
                                                
  ***  Claim Date: 10/31/11
  ***  Affidavite Date: 11/22/11
  ***  Counter Affidavite Due Date: 12/12/11
  ***  Counter Affidavite Date: 12/12/11
 

  
   Stop Notice #5 [ Back to Contract #04163734]     [ Top of Page ]  

  Claimant:
Abrasive Blasting & Coating, Inc.
1260 Railroad Ave, Bldg 750
Vallejo, CA  94592
                                                

    History:
Claim establisted for $155,681.81
on 12/16/2011 by s130442

Modify Claim - Letter of Release
 on 03/28/2012, by s130442
$62,500.00 Paymt to contract payee
New Claim $105,681.81
Schedule: 2DXXX460
Amended / revised stop notice.

Release Claim - Letter of Release
 on 05/17/2012, by s130442
$132,102.26 Paymt to contract payee
Schedule: 2DXXX540
                                                
  ***  Claim Date: 12/16/11
 

  
   Stop Notice #6 [ Back to Contract #04163734]     [ Top of Page ]  

  Claimant:
Jeffco Painting and Coating  Inc
P.O. Box 1888
Vallejo CA 94590
                                                

    History:
Claim establisted for $599,807.07
on 01/18/2012 by s130442

Release Claim - Letter of Release
 on 02/09/2012, by s130442
$749,758.84 Paymt to contract payee
Schedule: 2DXXX380
                                                
  ***  Claim Date: 01/18/12
 

  
   Stop Notice #7 [ Back to Contract #04163734]     [ Top of Page ]  

  Claimant:
Schwager Davis, Inc.
198 Hillsdale Avenue
San Jose, CA 95136
                                                

    History:
Claim establisted for $85,379.54
on 02/24/2012 by s130442

Release Claim - Legal Dept.
 on 11/15/2012, by s130442
$106,724.43 Paymt to contract payee
Schedule: 3DXXX310
Per legal, no law suit filed.
                                                
  ***  Claim Date: 02/24/12
 

  
   Stop Notice #8 [ Back to Contract #04163734]     [ Top of Page ]  

  Claimant:
Pio's Trucking, Inc.
1101 Wright Avenue
Richmond,  CA  94804
                                                

    History:
Claim establisted for $12,739.54
on 04/11/2012 by s130442

Release Claim - Letter of Release
 on 07/23/2012, by s130442
$6,054.59 Paymt to contract payee
Schedule: 3DXXX010
                                                
  ***  Claim Date: 04/10/12
 

  
   Stop Notice #9 [ Back to Contract #04163734]     [ Top of Page ]  

  Claimant:
ED Safety Service
1040 W. kettleman Lane, 1B # 388
Lodi, CA 95240
                                                

    History:
Claim establisted for $202,943.44
on 06/01/2012 by s130442

Modify Claim - Letter of Release
 on 06/08/2012, by s130442
$0.00 Paymt to contract payee
New Claim $145,143.26
Amended / revised stop notice.

Modify Claim - Letter of Release
 on 07/25/2012, by s134388
$51,985.77 Paymt to contract payee
New Claim $103,554.65
Schedule: 3DXXX020
 Amended / revised SN

Modify Claim - Letter of Release
 on 11/02/2012, by s134388
$119,107.49 Paymt to contract payee
New Claim $8,268.66
Schedule: 3DXXX280
Amended Stop Notice 

Release Claim - Legal Dept.
 on 11/15/2012, by s130442
$10,335.83 Paymt to contract payee
Schedule: 3DXXX310
Per legal, no law suit filed.
                                                
  ***  Claim Date: 05/30/12
 

  
   Stop Notice #10 [ Back to Contract #04163734]     [ Top of Page ]  

  Claimant:
Central Concrete Supply Co., Inc.
dba Westside Building Materials
755 Stockton Ave.
San Jose, CA 95126-1837
                                                

    History:
Claim establisted for $3,067.36
on 06/08/2012 by s130442

Release Claim - Legal Dept.
 on 01/02/2013, by s130442
$3,834.20 Paymt to contract payee
Schedule: 3DXXX410
Per legal, lawsuit dismissed.
                                                
  ***  Claim Date: 06/06/12
  ***  Suit Date: 07/27/12
 

  
   Stop Notice #11 [ Back to Contract #04163734]     [ Top of Page ]  

  Claimant:
Jim Freethy Excavating Inc
122 La Questa Drive
Danville, CA 94526
                                                

    History:
Claim establisted for $7,167.50
on 06/21/2012 by s134388

Release Claim - Letter of Release
 on 08/23/2012, by s130442
$8,959.38 Paymt to contract payee
Schedule: 3DXXX100
                                                
  ***  Claim Date: 06/20/12
 

  
   Stop Notice #12 [ Back to Contract #04163734]     [ Top of Page ]  

  Claimant:
Cemex Construction Materials
Pacific, LLC
5180 Golden Foothill Parkway, Ste 200
El Dorado Hills, CA  95762
                                                

    History:
Claim establisted for $7,895.87
on 07/20/2012 by s130442

Release Claim - Legal Dept.
 on 11/15/2012, by s130442
$9,869.84 Paymt to contract payee
Schedule: 3DXXX310
Per legal, no law suit filed.
                                                
  ***  Claim Date: 07/20/12
 

  
   Stop Notice #13 [ Back to Contract #04163734]     [ Top of Page ]  

  Claimant:
Roadway Engineering Works, Inc
3442 6th St
Ceres, CA 95307
                                                

    History:
Claim establisted for $81,723.23
on 07/26/2012 by s130442

Modify Claim - Letter of Release
 on 10/05/2012, by s130442
$55,912.88 Paymt to contract payee
New Claim $36,992.93
Schedule: 3DXXX200
Amended / revised stop notice.

Modify Claim - Letter of Release
 on 11/08/2012, by s129656
$37,429.49 Paymt to contract payee
New Claim $7,049.34
Schedule: 3DXXX300
Amended stop notice.

Release Claim - Legal Dept.
 on 11/15/2012, by s130442
$8,811.68 Paymt to contract payee
Schedule: 3DXXX310
Per legal, no law suit filed.
                                                
  ***  Claim Date: 07/26/12
 

  

 
Return to Search Page