State of California
DEPARTMENT OF TRANSPORTATION
Major Construction Payment & Information System
Stop Notice History for Contract 040060A4
|
Claimant:
XKT Engineering, Inc.
P.O. Box 152
Vallejo, CA 94590 -
|
History:
Claim establisted for $51,997.42
on 10/27/2008 by lvallejo
Release Claim - Letter of Release
on 11/07/2008, by lvallejo
$64,996.78 Paymt to contract payee
Schedule: 9D997140
-
*** Claim Date: 10/22/08
-
|
| |
|
Claimant:
Hammer & Steel, Inc.
c/o Blakeley & Blakeley LLP
1000 Quail Street, Suite 200
Newport Beach, CA 92660 -
|
History:
Claim establisted for $51,027.11
on 03/17/2009 by lvallejo
Release Claim - Letter of Release
on 05/04/2009, by s129656
$63,783.89 Paymt to contract payee
Schedule: 9D997380
-
*** Claim Date: 03/17/09
-
|
| |
|
Claimant:
Cowan & Thompson Construction, Inc.
PO Box 1514
Martinez, CA 94553 -
|
History:
Claim establisted for $10,508.83
on 12/01/2009 by s130442
Release Claim - Letter of Release
on 02/01/2010, by s130442
$0.00 Paymt to contract payee
-
*** Claim Date: 11/24/09
-
|
| |
|
Claimant:
Hertz Equipment Rental Corp.
14501 Hertz Quail Springs Parkway
Oklahoma City, OK 73134 -
|
History:
Claim establisted for $2,990.11
on 12/21/2009 by s130442
Release Claim - Letter of Release
on 02/19/2010, by s130442
$0.00 Paymt to contract payee
-
*** Claim Date: 12/15/09
-
|
| |
|
Claimant:
Green Vista Landscape
7351 Galilee Road, Suite #190
Roseville, CA 95678 -
|
History:
Claim establisted for $34,623.20
on 02/16/2010 by s130442
Modify Claim - Letter of Release
on 03/08/2010, by s130442
$16,483.50 Paymt to contract payee
New Claim $21,436.40
Schedule: 0D997330
Amended / revised stop notice.
Release Claim - Letter of Release
on 06/23/2010, by s130442
$26,795.50 Paymt to contract payee
Schedule: 0D997470
-
*** Claim Date: 02/15/10
-
|
| |