   Stop Notice #1 [ Back to Contract #033E1004]     [ Top of Page ]  

  Claimant:
Ulmer Industries, Inc.
P. O. Box 2299
Glendora, CA 91740
                                                

    History:
Claim establisted for $1,580.25
on 07/16/2015 by s130442

Release Claim - Late Counter Affidavit
 on 12/27/2016, by s130442
$0.00 Paymt to contract payee
No counter affidavit received as of 12/27/16.

Release Claim - Letter of Release
 on 04/13/2017, by s130442
$1,975.31 Paymt to contract payee
Schedule: 7DXXX490
Need to release funds for previously released s/n due to system glitch.
                                                
  ***  Claim Date: 07/14/15
  ***  Affidavite Date: 11/22/16
  ***  Counter Affidavite Due Date: 12/12/16
  ***  No Counter Affidavite on file
 

  
   Stop Notice #2 [ Back to Contract #033E1004]     [ Top of Page ]  

  Claimant:
W C Maloney, Inc
PO Box 30326
Stockton, CA 95213
                                                

    History:
Claim establisted for $137,753.31
on 07/22/2016 by s130442

Release Claim - Letter of Release
 on 08/31/2016, by s130442
$172,191.64 Paymt to contract payee
Schedule: 7DXXX120
                                                
  ***  Claim Date: 07/22/16
 

  
   Stop Notice #3 [ Back to Contract #033E1004]     [ Top of Page ]  

  Claimant:
ABSL Construction , Inc
29393 Pacific Street
Hayward  CA  94544
                                                

    History:
Claim establisted for $21,250.00
on 09/16/2016 by s130442

Release Claim - Letter of Release
 on 09/28/2016, by s130442
$0.00 Paymt to contract payee
                                                
  ***  Claim Date: 09/16/16
 

  
   Stop Notice #4 [ Back to Contract #033E1004]     [ Top of Page ]  

  Claimant:
ACL Construction Co., Inc.
PO Box 1929
Chino Hills, CA  91709
                                                

    History:
Claim establisted for $19,343.45
on 11/08/2016 by s130442

Modify Claim - Letter of Release
 on 11/18/2016, by s130442
$0.00 Paymt to contract payee
New Claim $19,068.94
Amended / revised stop payment notice.

Release Claim with Assignment
 on 02/20/2018, by S130442
$19,068.94 Paymt to assignee
$4,767.24 Paymt to contract payee
Schedule: 8DXXX034
Per legal, interpleader. funds to Superior Court County of Alameda.
                                                
  ***  Claim Date: 11/07/16
  ***  Suit Date: 05/17/17
 

  
   Stop Notice #5 [ Back to Contract #033E1004]     [ Top of Page ]  

  Claimant:
West Coast Water & Trucking, Inc.
3941 Park Dr., Suite # 20-231
El Dorado Hills, CA  95762
                                                

    History:
Claim establisted for $6,484.00
on 11/22/2016 by s130442

Release Claim - Legal Dept.
 on 06/30/2017, by 
$8,105.00 Paymt to contract payee
Schedule: 7DXXX580
Per Legal, no lawsuit filed.
                                                
  ***  Claim Date: 10/21/16
 

  

 