Contract: 112N0084
FEC Future Contractor's and Engineers, I

Date last updated: 11/20/24
  • Job Description: 
    REHABILITATE BRIDGE DECK IN IMPERIAL COUNTY AT VARIOUS LOCATIONS. 2IMP0007 0004 0063
  • Contract Accepted: 01/05/23
  • Stop Notice filing deadline: 04/05/23
  • Expiration of Suit-filing period: 07/04/23
  • Estimated Completion:  100%
  • Current Withhold Obligations: ....  $0.00
  • Curently Held:  ................................ $0.00
  • Need to Hold:  ................................  $0.00
  • Surety:
                Old Republic Surety Company
                14728 Pipeline Ave. #E Chino Hills, CA 91709
  • Bond Number: WCN2147392.
 

Withholds

Stop Notice
Filed Claim Amount Withhold Claimant
11/02/22
Released
 
12/08/22
Released
 
12/09/22
Released
 
12/09/22
Released
 
01/06/23
Released
 
02/15/23
Released
 
Total Stop Notice $0.00  
 
Please direct Stop Notice Inquiries to:
  Contact:  stop.notice.occp@dot.ca.gov
 Phone: (279) 234-2745


 
 
 

Payments


Detail estimate information is available for those issued after February 1,1999 while voucher payment data is available for those issued after July 1, 2000.  For detail estimate and voucher inquiries prior to the above dates please contact the Resident Engineer or the District Construction office.

The Held and Disbursed columns may include monies withheld or released for stop notices, legal, liens, levies, labor compliance and accounts receivable claims.

Payment History
Est. Engineering Contract Data Type Pmt Type Released Held Disbursed
1 Detail  Voucher  P/P  Warrant 10/04/21 0.00 355,684.96
2 Detail  Voucher  P/P  EFT 11/03/21 0.00 35,654.13
3 Detail  Voucher  P/P  EFT 12/06/21 0.00 151,458.26
4 Detail  Voucher  P/P  EFT 01/03/22 0.00 1,385,383.72
5 Detail  Voucher  P/P  EFT 02/03/22 0.00 510,082.17
6 Detail  Voucher  P/P  EFT 03/03/22 0.00 229,349.42
7 Detail  Voucher  P/P  EFT 04/01/22 0.00 252,753.08
8 Detail  Voucher  P/P  EFT 05/05/22 0.00 103,202.39
9 Detail  Voucher  P/P  EFT 06/03/22 0.00 386,067.82
10 Detail  Voucher  P/P  EFT 06/29/22 0.00 46,769.34
11 Detail  Voucher  P/P  EFT 08/03/22 0.00 74,490.17
12 Detail  Voucher  P/P  EFT 09/01/22 0.00 117,965.15
13 Detail  Voucher  P/P  EFT 09/12/22 0.00 35,950.00
14 Detail  Voucher  P/P  EFT 11/03/22 0.00 9,696.34
15 Detail  Voucher  P/P  Hold 12/09/22 4,612.86 0.00
16 Detail  Voucher  P/P  Hold 01/06/23 27,450.00 0.00
17 Detail  Voucher  A/A  Hold 02/22/23 15,339.71 0.00
18 Detail  Voucher  S/F  Hold 09/26/23 430,153.14 0.00
      SN 1 Release 10/24/23 -192,840.05 192,840.05
      SN 5 Release 10/24/23 -284,715.66 284,715.66
19 Detail  Voucher  FIN  Warrant 12/27/23 0.00 0.00
Total: $0.00 $4,172,062.66
 
Please direct Payment Inquiries to:
  Contact:  pisa.construction.payments.occp@dot.ca.gov
 Phone: (279) 234-2973












LEGEND:
Type Key
P/P  = Progress Payment
A/A = After Acceptance Payment
S/F  = Semi Final Payment
FIN  = Final Payment
 
Payment Type
Warrant = Check disbursement
EFT = Electronic Funds Transfer disbursement
SN # = Release Stop Notice Hold
LC # = Release Labor Compliance Hold
Legal # = Release Legal Hold
Dep # = Deposit previous disbursements
Hold = Held for future disbursement
Neg Est = Negative Estimate
A/R Coll = Accounts Receivable Collection
 



 
Return to Search Page