Contract: 052A0404
Brough Construction Inc.
Date last updated: 08/20/26
- Job Description:
RMV DMG WINGWALL,CONST RSP WALL & TC REMOVE DAMAGED WINGWALL, CONSTRUCT RSPWALL RESTORE FENCE AND TEMP TRAFFIC CONTROL RMV DMG WINGWALL,CONST RSP WALL & TC DIRS EFA 05A3002 2SLO0046 0420 0042 2SLO0046 0420 0042- Contract Accepted: 06/11/26
- Stop Notice filing deadline: 09/09/26
- Expiration of Suit-filing period: 12/08/26
- Estimated Completion: 100%
- Current Withhold Obligations: .... $0.00
- Currently Held: ................................ $0.00
- Need to Hold: ................................ $0.00
- Hold check in effect.
Payments
Detail estimate information is available for those issued after February
1,1999 while voucher payment data is available for those issued after July 1, 2000.
For detail estimate and voucher inquiries prior to the above dates please
contact the Resident Engineer or the District Construction office.
The Held and Disbursed columns may include monies withheld or released for stop notices, legal, liens, levies, labor compliance and accounts receivable claims.
The Held and Disbursed columns may include monies withheld or released for stop notices, legal, liens, levies, labor compliance and accounts receivable claims.
Payment History
| Est. | Engineering Contract Data | Type | Pmt Type | Released | Held | Disbursed | |
|---|---|---|---|---|---|---|---|
| 1 | Detail | Voucher | P/P | Warrant | 07/21/26 | 0.00 | 111,871.78 |
| 2 | Detail | Voucher | A/A | Neg Est | 08/18/26 | 0.00 | -20,000.00 |
| Total: | $0.00 | $91,871.78 | |||||
|