Contract: 042E3004
Anozira Incorporated
Date last updated: 09/12/24
- Job Description:
REPLACE PORTLAND CEMENT CONCRETE IN SOLANO COUNTY IN DIXON FROM 0.7 MILE EAST OF LEISURE TOWN ROAD OVERCROSSING TO 1.4 MILE WEST OF PEDRICK ROAD OVERCROSSING 2SOL0080 0306 0382- Contract Accepted: 03/03/11
- Stop Notice filing deadline: 06/01/11
- Expiration of Suit-filing period: 08/30/11
- Estimated Completion: 100%
- Current Withhold Obligations: .... $0.00
- Curently Held: ................................ $0.00
- Need to Hold: ................................ $0.00
- Surety:
- The Ohio Casualty Insurance Company
- 1340 Treat Boulevard, Suite 240 Walnut Creek, CA 94597
- Bond Number: 4-082-436.
Payments
Detail estimate information is available for those issued after February
1,1999 while voucher payment data is available for those issued after July 1, 2000.
For detail estimate and voucher inquiries prior to the above dates please
contact the Resident Engineer or the District Construction office.
The Held and Disbursed columns may include monies withheld or released for stop notices, legal, liens, levies, labor compliance and accounts receivable claims.
The Held and Disbursed columns may include monies withheld or released for stop notices, legal, liens, levies, labor compliance and accounts receivable claims.
Payment History
Est. | Engineering Contract Data | Type | Pmt Type | Released | Held | Disbursed | |
---|---|---|---|---|---|---|---|
1 | Detail | Voucher | P/P | Warrant | 03/15/11 | 0.00 | 351,530.80 |
2 | Detail | Voucher | A/A | Warrant | 03/29/11 | 0.00 | 0.00 |
3 | Detail | Voucher | FIN | Warrant | 06/01/11 | 0.00 | 1,760.00 |
Total: | $0.00 | $353,290.80 | |||||
Please direct Payment inquires to:
|