Contract: 04269604
Bay Cities Paving And Grading Inc
Date last updated: 09/12/24
- Job Description:
ROADWAY REHABILITATION IN CONTRA COSTA COUNTY IN LAFAYETTE AND ORINDA FROM THE CALDECOTT TUNNEL TO EL CURTOLA ROAD OVERCROSSING 2CC 0024R0001R0083- Contract Accepted: 04/17/09
- Stop Notice filing deadline: 07/16/09
- Expiration of Suit-filing period: 10/14/09
- Estimated Completion: 100%
- Current Withhold Obligations: .... $0.00
- Curently Held: ................................ $0.00
- Need to Hold: ................................ $0.00
- Surety:
- Safeco Insurance Company of America
- c/o Tanner Insurance Brokers 4670 Willow Road #250 Pleasanton, CA 94588
- Bond Number: 6474827.
Withholds
Stop Notice
Filed | Claim Amount | Withhold | Claimant |
---|---|---|---|
07/14/09 |
Released | ||
07/15/09 |
Released | ||
Total Stop Notice | $0.00 | ||
Please direct Stop Notice inquires to:
| |||
Payments
Detail estimate information is available for those issued after February
1,1999 while voucher payment data is available for those issued after July 1, 2000.
For detail estimate and voucher inquiries prior to the above dates please
contact the Resident Engineer or the District Construction office.
The Held and Disbursed columns may include monies withheld or released for stop notices, legal, liens, levies, labor compliance and accounts receivable claims.
The Held and Disbursed columns may include monies withheld or released for stop notices, legal, liens, levies, labor compliance and accounts receivable claims.
Payment History
Est. | Engineering Contract Data | Type | Pmt Type | Released | Held | Disbursed | |
---|---|---|---|---|---|---|---|
1 | Detail | Voucher | P/P | Warrant | 06/08/07 | 0.00 | 573,607.56 |
2 | Detail | Voucher | P/P | Warrant | 07/03/07 | 0.00 | 2,758,417.75 |
3 | Detail | Voucher | P/P | EFT | 08/03/07 | 0.00 | 3,944,031.80 |
4 | Detail | Voucher | P/P | EFT | 09/04/07 | 0.00 | 4,902,747.52 |
5 | Detail | Voucher | P/P | EFT | 10/04/07 | 0.00 | 5,368,451.27 |
6 | Detail | Voucher | P/P | EFT | 10/15/07 | 0.00 | 56,745.00 |
7 | Detail | Voucher | P/P | EFT | 11/02/07 | 0.00 | 4,462,206.68 |
8 | Detail | Voucher | P/P | EFT | 12/06/07 | 0.00 | 3,312,463.43 |
9 | Detail | Voucher | P/P | EFT | 01/07/08 | 0.00 | 799,626.67 |
10 | Detail | Voucher | P/P | EFT | 02/04/08 | 0.00 | 169,666.43 |
11 | Detail | Voucher | P/P | EFT | 03/05/08 | 0.00 | 570,757.49 |
12 | Detail | Voucher | P/P | EFT | 04/04/08 | 0.00 | 371,651.31 |
13 | Detail | Voucher | P/P | EFT | 06/04/08 | 0.00 | 1,039,753.98 |
14 | Detail | Voucher | P/P | EFT | 06/26/08 | 0.00 | 233,656.30 |
15 | Detail | Voucher | P/P | EFT | 08/01/08 | 0.00 | 799,807.52 |
16 | Detail | Voucher | P/P | EFT | 08/08/08 | 0.00 | 325,105.18 |
17 | Detail | Voucher | P/P | EFT | 09/04/08 | 0.00 | 2,150,914.37 |
18 | Detail | Voucher | P/P | EFT | 10/03/08 | 0.00 | 2,304,608.85 |
19 | Detail | Voucher | P/P | EFT | 11/03/08 | 0.00 | 1,662,566.31 |
20 | Detail | Voucher | P/P | EFT | 12/05/08 | 0.00 | 470,131.01 |
21 | Detail | Voucher | P/P | EFT | 01/06/09 | 0.00 | 49,275.07 |
22 | Detail | Voucher | P/P | EFT | 02/03/09 | 0.00 | 106,336.41 |
23 | Detail | Voucher | P/P | EFT | 03/06/09 | 0.00 | 606,293.11 |
24 | Detail | Voucher | P/P | EFT | 04/06/09 | 0.00 | 381,486.26 |
25 | Detail | Voucher | A/A | EFT | 05/01/09 | 0.00 | 231,257.33 |
26 | Detail | Voucher | S/F | Warrant | 08/25/09 | 0.00 | 356,069.60 |
26 | Detail | Voucher | S/F | Hold | 08/25/09 | 44,685.15 | 0.00 |
SN 2 Release | 10/23/09 | -39,868.36 | 39,868.36 | ||||
27 | Detail | Voucher | FIN | Warrant | 12/03/09 | 0.00 | 622,437.08 |
SN 1 Release | 12/10/09 | -4,816.79 | 4,816.79 | ||||
Total: | $0.00 | $38,674,756.44 | |||||