Major Construction Payment & Information

Contract Details

 
State of California  
DEPARTMENT OF TRANSPORTATION  
Major Construction Payment & Information System  
 
 

Contract: 022C1124
Proven Management Inc

Date last updated: 04/18/24
  • Job Description: 
    REPLACE BRIDGE IN TEHAMA COUNTY NEAR LOS MOLINOS FROM 0.1 MILE SOUTH OF SOUTH FORK MILL CREEK TO 0.1 MILE NORTH OF OF NORTH FORK MILL CREEK. 2TEH0099 0139 0143
  • Contract Accepted: 12/30/13
  • Stop Notice filing deadline: 03/30/14
  • Expiration of Suit-filing period: 06/28/14
  • Estimated Completion:  100%
  • Current Withhold Obligations: ....  $0.00
  • Curently Held:  ................................ $0.00
  • Need to Hold:  ................................  $0.00
  • Surety:
                Liberty Mutual Insurance Company
                1340 Treat Blvd. Suite 550 Walnut Creek, CA 94597
  • Bond Number: 070-014-614.
 

Withholds

Stop Notice
Filed Claim Amount Withhold Claimant
11/20/13
Released
 
01/22/14
Released
 
02/06/14
Released
 
02/12/14
Released
 
02/26/14
Released
 
03/17/14
Released
 
03/28/14
Released
 
03/28/14
Released
 
Total Stop Notice $0.00  
 
Please direct Stop Notice inquires to:
   Name: stop notice occp
 Phone: (279)234-2745
     Fax: (916) 227-9736
  E-Mail:  stop.notice.occp@dot.ca.gov

 
 
 

Payments


Detail estimate information is available for those issued after February 1,1999 while voucher payment data is available for those issued after July 1, 2000.  For detail estimate and voucher inquiries prior to the above dates please contact the Resident Engineer or the District Construction office.

The Held and Disbursed columns may include monies withheld or released for stop notices, legal, liens, levies, labor compliance and accounts receivable claims.

Payment History
Est. Engineering Contract Data Type Pmt Type Released Held Disbursed
1 Detail  Voucher  P/P  Warrant 08/05/13 0.00 14,875.00
2 Detail  Voucher  P/P  Warrant 09/06/13 0.00 706,928.50
3 Detail  Voucher  P/P  Warrant 10/03/13 0.00 437,447.50
4 Detail  Voucher  P/P  Warrant 11/04/13 0.00 437,000.35
5 Detail  Voucher  P/P  Warrant 12/09/13 0.00 91,902.15
5 Detail  Voucher  P/P  Hold 12/09/13 35,507.55 0.00
6 Detail  Voucher  P/P  Warrant 01/07/14 0.00 17,285.50
7 Detail  Voucher  A/A  Neg Est 01/29/14 0.00 -4,739.95
8 Detail  Voucher  A/A  A/R Coll 02/04/14 0.00 4,739.95
8 Detail  Voucher  A/A  Hold 02/04/14 4,260.05 0.00
9 Detail  Voucher  S/F  Warrant 02/26/14 0.00 8,236.47
9 Detail  Voucher  S/F  Hold 02/26/14 23,907.40 0.00
10 Detail  Voucher  S/F  Warrant 04/22/14 0.00 10,803.23
10 Detail  Voucher  S/F  Hold 04/22/14 64,887.50 0.00
      SN 4 Release 06/17/14 -10,667.45 10,667.45
      SN 6 Release 06/19/14 -5,750.00 5,750.00
      SN 7 Release 06/19/14 -1,100.00 1,100.00
11 Detail  Voucher  FIN  Warrant 06/10/14 0.00 70,280.66
      SN 8 Release 07/17/14 -25,556.25 25,556.25
      SN 1 Release 08/06/14 -35,507.55 35,507.55
      SN 3 Release 08/18/14 -17,500.00 17,500.00
      SN 5 Release 08/18/14 -32,481.25 32,481.25
Total: $0.00 $1,923,321.86
 
Please direct Payment inquires to:
   Name: pisa construction payments occp
 Phone: (279)234-2973
     Fax: (916) 227-9736
  E-Mail:  pisa.construction.payments.occp@dot.ca.gov











LEGEND:
Type Key
P/P  = Progress Payment
A/A = After Acceptance Payment
S/F  = Semi Final Payment
FIN  = Final Payment
 
Payment Type
Warrant = Check disbursement
EFT = Electronic Funds Transfer disbursement
SN # = Release Stop Notice Hold
LC # = Release Labor Compliance Hold
Legal # = Release Legal Hold
Dep # = Deposit previous disbursements
Hold = Held for future disbursement
Neg Est = Negative Estimate
A/R Coll = Accounts Receivable Collection
 



 
Return to Search Page