Contract: 020E8004
SGC Construction
Date last updated: 11/20/24
- Job Description:
HOOK UP WATER AND SEWER SUPPLY IN TEHAMA COUNTY IN AND NEAR CORNING FROM 0.5 MILE SOUTH OF GALLAGHER OVERCROSSING TO AND AT CORNING SAFETY ROADSIDE REST AREA 2TEH0005 0095 0105- Contract Accepted: 05/11/11
- Stop Notice filing deadline: 08/09/11
- Expiration of Suit-filing period: 11/07/11
- Estimated Completion: 100%
- Current Withhold Obligations: .... $0.00
- Curently Held: ................................ $0.00
- Need to Hold: ................................ $0.00
- Surety:
- American Contractors Indemnity Company
- 601 Figueroa St., Ste 1600 Los Angeles, CA 90017
- Bond Number: 1000842468.
Withholds
Stop Notice
Filed | Claim Amount | Withhold | Claimant |
---|---|---|---|
11/05/10 |
Released | ||
11/05/10 |
Released | ||
11/05/10 |
Released | ||
11/08/10 |
Released | ||
11/10/10 |
Released | ||
11/18/10 |
Released | ||
11/20/10 |
Released | ||
11/23/10 |
Released | ||
11/30/10 |
Released | ||
12/22/10 |
Released | ||
12/22/10 |
Released | ||
12/22/10 |
Released | ||
12/22/10 |
Released | ||
Total Stop Notice | $0.00 | ||
Please direct Stop Notice Inquiries to:
| |||
Payments
Detail estimate information is available for those issued after February
1,1999 while voucher payment data is available for those issued after July 1, 2000.
For detail estimate and voucher inquiries prior to the above dates please
contact the Resident Engineer or the District Construction office.
The Held and Disbursed columns may include monies withheld or released for stop notices, legal, liens, levies, labor compliance and accounts receivable claims.
The Held and Disbursed columns may include monies withheld or released for stop notices, legal, liens, levies, labor compliance and accounts receivable claims.
Payment History
Est. | Engineering Contract Data | Type | Pmt Type | Released | Held | Disbursed | |
---|---|---|---|---|---|---|---|
1 | Detail | Voucher | P/P | Warrant | 08/05/10 | 0.00 | 33,257.20 |
2 | Detail | Voucher | P/P | Warrant | 09/10/10 | 0.00 | 168,101.77 |
3 | Detail | Voucher | P/P | Warrant | 10/06/10 | 0.00 | 125,082.68 |
4 | Detail | Voucher | P/P | Warrant | 10/26/10 | 0.00 | 27,074.67 |
5 | Detail | Voucher | P/P | Warrant | 11/09/10 | 0.00 | 118,326.06 |
Dep 001 | 11/05/10 | 0.00 | -118,326.06 | ||||
Dep 001 Hold | 11/05/10 | 118,326.06 | 0.00 | ||||
6 | Detail | Voucher | P/P | Hold | 01/26/11 | 82,414.65 | 0.00 |
SN 2 Release | 03/22/11 | -3,488.59 | 3,488.59 | ||||
SN 1 Release | 03/22/11 | -83,155.69 | 83,155.69 | ||||
SN 6 Release | 03/22/11 | -20,035.63 | 20,035.63 | ||||
SN 11 Release | 05/02/11 | -3,674.66 | 3,674.66 | ||||
Dep 002 | 04/14/11 | 0.00 | -3,674.66 | ||||
Dep 002 Hold | 04/14/11 | 3,674.66 | 0.00 | ||||
SN 13 Release | 05/02/11 | -3,674.66 | 3,674.66 | ||||
SN 10 Release | 05/26/11 | -11,875.00 | 11,875.00 | ||||
7 | Detail | Voucher | A/A | Warrant | 06/01/11 | 0.00 | 46,458.00 |
8 | Detail | Voucher | S/F | Warrant | 06/21/11 | 0.00 | 20,000.00 |
9 | Detail | Voucher | S/F | Warrant | 08/30/11 | 0.00 | 14,510.73 |
10 | Detail | Voucher | FIN | Warrant | 12/13/11 | 0.00 | 2,000.00 |
SN 7 Release | 01/04/12 | -78,511.14 | 78,511.14 | ||||
Total: | $0.00 | $637,225.76 | |||||