Contract: 010B27U4
Stewart Engineering Inc

Date last updated: 04/18/24
  • Job Description: 
    REPAIR STORM DAMAGE IN DEL NORTE COUNTY ABOUT 10 MILES NORTH OF KLAMATH FROM 2.2 MILES TO 2.6 MILES NORTH OF WILSON CREEK BRIDGE 2DN 0101 0149 0153
  • Contract Accepted: 01/18/18
  • Stop Notice filing deadline: 04/18/18
  • Expiration of Suit-filing period: 07/17/18
  • Estimated Completion:  100%
  • Current Withhold Obligations: ....  $0.00
  • Curently Held:  ................................ $0.00
  • Need to Hold:  ................................  $0.00
  • Surety:
                The Guarantee Company of North America
                One Town Square, Suite 1470 Southfield, MI 48076
  • Bond Number: 12132580.
 

Payments


Detail estimate information is available for those issued after February 1,1999 while voucher payment data is available for those issued after July 1, 2000.  For detail estimate and voucher inquiries prior to the above dates please contact the Resident Engineer or the District Construction office.

The Held and Disbursed columns may include monies withheld or released for stop notices, legal, liens, levies, labor compliance and accounts receivable claims.

Payment History
Est. Engineering Contract Data Type Pmt Type Released Held Disbursed
1 Detail  Voucher  P/P  Warrant 08/05/16 0.00 108,695.40
2 Detail  Voucher  P/P  EFT 09/01/16 0.00 737,812.93
3 Detail  Voucher  P/P  EFT 09/12/16 0.00 44,880.00
4 Detail  Voucher  P/P  EFT 09/29/16 0.00 365,349.05
5 Detail  Voucher  P/P  EFT 11/03/16 0.00 228,196.18
6 Detail  Voucher  P/P  EFT 12/06/16 0.00 408,892.28
7 Detail  Voucher  P/P  EFT 01/05/17 0.00 203,966.74
8 Detail  Voucher  P/P  EFT 03/06/17 0.00 89,375.25
9 Detail  Voucher  P/P  EFT 05/04/17 0.00 20,595.11
10 Detail  Voucher  P/P  EFT 06/29/17 0.00 176,632.38
11 Detail  Voucher  P/P  EFT 08/03/17 0.00 254,015.45
12 Detail  Voucher  P/P  EFT 08/31/17 0.00 318,527.58
13 Detail  Voucher  P/P  EFT 10/06/17 0.00 504,547.11
14 Detail  Voucher  P/P  EFT 11/02/17 0.00 165,574.25
15 Detail  Voucher  P/P  EFT 11/13/17 0.00 95,000.00
16 Detail  Voucher  P/P  EFT 12/06/17 0.00 54,284.00
17 Detail  Voucher  P/P  EFT 01/05/18 0.00 55,382.17
18 Detail  Voucher  A/A  EFT 02/26/18 0.00 5,260.96
19 Detail  Voucher  FIN  EFT 04/13/18 0.00 14,000.00
Total: $0.00 $3,850,986.84
 
Please direct Payment inquires to:
   Name: pisa construction payments occp
 Phone: (279)234-2973
     Fax: (916) 227-9736
  E-Mail:  pisa.construction.payments.occp@dot.ca.gov











LEGEND:
Type Key
P/P  = Progress Payment
A/A = After Acceptance Payment
S/F  = Semi Final Payment
FIN  = Final Payment
 
Payment Type
Warrant = Check disbursement
EFT = Electronic Funds Transfer disbursement
SN # = Release Stop Notice Hold
LC # = Release Labor Compliance Hold
Legal # = Release Legal Hold
Dep # = Deposit previous disbursements
Hold = Held for future disbursement
Neg Est = Negative Estimate
A/R Coll = Accounts Receivable Collection
 



 